JNE — Data Center Relocation

End-to-end database migration across data centers with mixed endian formats

OracleOracle Data GuardData PumpCross-endian

Overview

JNE Express needed to relocate production database workloads from a legacy data center to a new facility. Some servers shared the same endian format as the target hardware; others required a cross-endian migration. Either way, downtime had to be kept to a tight cut-off window during low-traffic hours.

Approach

Same-endian path — Oracle Data Guard switchover

  • Created Oracle Data Guard (ODG) with the old DC as primary and the new DC as standby.
  • Verified that ODG was fully synchronized and gap-free before initiating the switchover.

Cross-endian path — Data Pump migration

  • For databases moving from big-endian to little-endian platforms, executed migration via Data Pump export/import.
  • Handled data lag during the export-import window with scheduled jobs and procedural catch-up.

Cut-off and validation

  • After confirming zero lag, performed the production cut-off and DB switchover to the new data center.
  • Verified connectivity and access from every dependent service.
  • Ran stress tests and load tests against the new environment.
  • Delivered post-migration documentation and evaluation reports.

Outcome

Both migration paths completed within their cut-off windows. The new data center took over production traffic without data loss, and performance benchmarks met or exceeded the baseline.